Place a perforated drainage pipe 2 inches up from ground.
Making your own stackable concrete pavers retaining wall.
If the wall runs up a hill continue each base course of stackable retaining wall blocks into the hill until the top of the second course is level with the grade and then start your second base course at that point.
However if you want you can even make your own molds out of plywood.
With the layout marked you can begin digging the trench.
Molds for cement pavers are available in most large hardware stores.
Dig for the first row of block.
In this video i showed how you can make your own concrete stacked stone at home.
Position your first block and use a standard level to make sure it s even.
After you finish the first course fill the space between your retaining wall and.
Work gloves shovel and or mattock brick chisel and small sledgehammer level wooden stakes string and a line level soil tamper gravel sharp not rounded or rock dust landscape fabric optional interlocking stackable stones and toppers.
Stacked stone concrete mold used https amzn to 2leczrs for more details o.
For row one knock off the flanges with a hammer and chisel so the.
Prepare the foundation step 1.
If stacking pavers to retain soil and the wall is more than two feet high backfill a couple inches directly behind the wall with gravel.
If you have the option it can be easier to excavate and lay the lowest course before excavating the trench for the next step.
For dry stack walls the base should be as wide as the wall is tall.
Remember one mold makes only one cement paver and it will take at least two weeks before your cement paver is ready for use.
To bury the first row.
The exact depth of the.
For this project you will need.
For this 18 inch high wall the footing should be at least 18 inches wide.
For a stacked block retaining wall that s no higher than four feet a trench filled with three inches of crushed rock will help keep the wall from shifting and settling.
Whatever your choice do ensure that you have lots of molds.
Continue laying your first course of blocks making sure to check that every block is level.
Use a hand or power tamper to level the base.